2003 West Wing Construction

  • April 18: We begin the project
  • April 21-23: Removing the existing parking lot
  • May 1: Relocating the palm trees
  • May 16: Installing the new sewer line
  • May 25: The big dig
  • May 27: Renovating the teaching labs
  • June: The big dig continues
  • July: The caissons and the mock-up
  • August, September and October: The foundation
  • November: The third floor walls
  • December: Third floor construction